This page summarizes the current validation state of Orgo without replacing the detailed technical evidence kept in the main repository documentation.
Current development status
As of 2026-09-17, the current Orgo development tree has passed the complete local automated validation chain available in LevelUpDiag:
| Campaign | Result | What it establishes |
|---|---|---|
database |
PASS | Native PostgreSQL migration and database integration validation |
deep |
PASS | Architecture, types, tests, production builds, dependency audit and related repository checks |
browser |
PASS | Required Chromium journeys against a real local Orgo API and PostgreSQL runtime |
acceptance |
PASS | Backup/restore plus an isolated production-like Docker deployment and browser acceptance |
The successful acceptance run completed 9/9 required levels with no warnings, failures, errors or blocked levels.
Production-like acceptance evidence
The automated acceptance path validated:
- repository-shipped PostgreSQL backup and restore procedures;
- restoration of 70/70 expected tables;
- restoration of the expected Prisma migration history (1/1 migration record in the acceptance database);
- startup of an isolated Docker Compose stack containing PostgreSQL, API, web and worker services;
- API, web and worker health checks;
- disposable account/seed preparation;
- 24/24 Chromium browser journeys against that isolated stack;
- automatic cleanup of the temporary containers, network and volume;
- dependency audit reporting 0 vulnerabilities for the validated dependency state.
Dynamic loopback ports are used by the acceptance harness so the production-like stack does not require the normal development ports to be free.
Release baseline
The published tagged baseline remains:
v0.1.0-rc.1
That tag is an immutable historical release-candidate baseline. The newer 2026-09-17 acceptance evidence applies to the later development tree and does not by itself move, replace or promote the RC1 tag.
A future RC or production release should be cut intentionally from an identified clean commit with its validation evidence retained for that exact state.
What is not claimed
The green local acceptance chain is strong production-like evidence, but it is not the same as a real production deployment.
This status does not claim live interoperability with deployment-specific external providers that were not configured during acceptance, including for example:
- SMTP or SMS providers;
- external webhooks;
- a real OIDC Identity Provider;
- Konnaxion / kOA ecosystem services;
- Kristal / Da’at integrations;
- other provider-specific credentials or hosted infrastructure.
Those remain separate acceptance boundaries when a deployment enables them.
Practical interpretation
Orgo's current development tree is locally production-acceptance green for the automated scope above.
The next release step is not another generic local test pass; it is to identify the exact release commit, retain its evidence, and then intentionally decide whether to cut a new release candidate or production release.